GILLOOLY’S INTERCHANGE TO RIETFONTEIN INTERCHANGE
JOHANNESBURG, SA
Assignment: Forensic Schedule Delay Analysis and Expert Witness reports for entitlement to Extension of Time and associated costs incurred by CMC.
Outcome; Successful
MIXED USE SKYSCRAPER
1 WEST INDIA QUAY
Assignment: Forensic Schedule Delay Analysis
Multiplex – Working with a dedicated team to assess entitlement to ‘Extension of Time’ and associated costs through forensic planning for No. 1 West India Quay.
Very few records and no programme available, therefore created a project programme from scratch to assess delays.
Outcome; awarded EOT and associated costs.
PLYMOUTH TO PENZANCE FIBRE OPTIC & COPPER CABLE ROUTES
Assignment: Forensic Schedule Delay Analysis and expert reports for entitlement for additional costs incurred by Birse Rail in completion of the Plymouth to Penzance main line for the construction of fibre optic and copper cable routes and base station sites.
Outcome; Successful
MIXED USE SKYSCRAPER
KINGDOM CENTRE RIYADH
Assignment: Forensic Schedule Delay Analysis.
Severe delays encountered due to the collapse of the main entrance.
Produce an expert ‘defence’ document on behalf of the contractor (El Seif). Kingdom Centre in Riyadh, Saudi Arabia.
Outcome; Unknown
POWER STATIONS
ABERTHAW COAL FIRED POWER STATION
EDMUND NUTTALL – 11th Jan’08 – 22nd Aug’08
Assignment: Forensic Schedule Delay Analysis and expert report for Extension of Time and associated additional costs incurred by Edmund Nuttall.
Project: Aberthaw Power Station
Construction Manager: AMEC: Client: RWE AG: Legal Adviser: Shadbolt LLP
Outcome; Successful
UNDERGROUND RAIL
EUSTON UNDERGROUND STATION MODERNISATION
TUBE LINES (TLL) 23rd February 2009 – 11th December 2009
Assignment: Forensic Schedule Delay Analysis and expert review and reports for entitlement to additional costs incurred by Tube Lines in completion of the Euston Station and Southgate Station Modernisation projects.
Client: London Underground (Transport for London) – capital works programme
Working with LUL: Bechtel
Outcome; Successful
KAJIMA CONSTRUCTION EUROPE (UK) LTD
HSBC BUILDING
Assignment: Forensic Schedule Delay Analysis
Forensic planning to defend Kajima’s liabilities on the new HSBC building in St James’s., London.
The dispute was centred on resourcing issues.
Extensive task-level resource analysis was used to successfully resolve the dispute.
Outcome; Successful